On May 10th, 2017, the final reception for the objective “Closing down noncompliant waste deposit in Ploiesti” took place. The objective is part of the project “Integrated waste management system in Prahova county”.

The executed works were cofinanced though SOP Environment 2007 – 2013.

Closing down the noncompliant waste deposit in Ploiest led to the rehabilitation and recovery of 31 ha of field. It also led to reducing the environmental pollution as results of domestic slides of wastes on Teleajen river, in times of heavy rain.

The total value of the project: 19,926,609.24 lei.

 

ROMAIR Consulting, as Consultant, prepared the Master Plan  for the above mentioned project and drafted the application form which led to signing the contract. The financing contract had a total value of 203,238,610.37 lei and it was signed in February 2013. Also, ROMAIR Consulting was the Designer, drafting the Technical design  and the tender documentation, including the technical assistance services on behalf of the designer during the execution of works.

The efforts of the team of engineers in the company, during a period of 7 years, led to the final receptions of the investments. Thus, we are pleased to see that the old waste deposit was reintroduced in the natural circuit.